Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:49:07.017331
Works ongoing
71
Sanctioned (pure scheme)
₹1.66 Cr
Expenditure since inception
₹77.57 L
Balance cost (unspent)
₹88.30 L
Wage ₹62.23 L · Material ₹26.08 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
3 works
₹43.04 L sanctioned
₹27.18 L spent (63%)
02
Constr of Cement Concrete Roads
2 works
₹38.06 L sanctioned
₹16.53 L spent (43%)
03
Plantation
5 works
₹21.31 L sanctioned
₹6.43 L spent (30%)
04
Farm Pond
10 works
₹19.24 L sanctioned
₹8.08 L spent (42%)
05
Construction of Bund
2 works
₹13.35 L sanctioned
₹6.41 L spent (48%)
06
Rural Housing
43 works
₹11.61 L sanctioned
₹8.07 L spent (69%)
07
Constr of Gabion
1 works
₹9.49 L sanctioned
₹2.44 L spent (26%)
08
Construction of Well
2 works
₹6.78 L sanctioned
₹1.89 L spent (28%)
09
Repair & maint of Pond/ Tank
2 works
₹2.56 L sanctioned
₹31,824 spent (12%)
10
Community Sanitary Complex
1 works
₹44,000 sanctioned
₹23,085 spent (52%)