Monitor — Ongoing Works
Rollup last refreshed: 2026-10-15 06:57:05.982177
Works ongoing
19
Sanctioned (pure scheme)
₹90.23 L
Expenditure since inception
₹44.07 L
Balance cost (unspent)
₹46.16 L
Wage ₹23.15 L · Material ₹23.01 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
3 works
₹27.55 L sanctioned
₹13.25 L spent (48%)
02
Plantation
7 works
₹18.66 L sanctioned
₹75,392 spent (4%)
03
Construction of Spur
1 works
₹14.41 L sanctioned
₹14.20 L spent (99%)
04
Construction of Bund
1 works
₹10.36 L sanctioned
₹5.44 L spent (52%)
05
Constr of Gabion
1 works
₹7.17 L sanctioned
₹5.13 L spent (72%)
06
Construction of Well
2 works
₹5.79 L sanctioned
₹3.73 L spent (65%)
07
Well Recharge
2 works
₹5.75 L sanctioned
₹1.25 L spent (22%)
08
Rural Housing
2 works
₹54,000 sanctioned
₹30,209 spent (56%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)