Monitor — Ongoing Works
Rollup last refreshed: 2026-09-04 06:52:37.03894
Works ongoing
53
Sanctioned (pure scheme)
₹1.74 Cr
Expenditure since inception
₹72,000
Balance cost (unspent)
₹1.73 Cr
Wage ₹95.19 L · Material ₹77.95 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
20 works
₹92.23 L sanctioned
₹72,000 spent (1%)
02
Plantation
14 works
₹35.11 L sanctioned
₹0 spent (0%)
03
Construction of Road and Culvert
1 works
₹24.02 L sanctioned
₹0 spent (0%)
04
Constr of Gabion
2 works
₹11.38 L sanctioned
₹0 spent (0%)
05
Rural Housing
12 works
₹3.18 L sanctioned
₹0 spent (0%)
06
Farm Pond
1 works
₹2.43 L sanctioned
₹0 spent (0%)
07
Construction of Other Community Building/Assets
1 works
₹2.37 L sanctioned
₹0 spent (0%)
08
Construction of Crematorium
1 works
₹2.35 L sanctioned
₹0 spent (0%)
09
Constr of Cement Concrete Roads
1 works
₹80,000 sanctioned
₹0 spent (0%)
10
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)