Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
20
Sanctioned (pure scheme)
₹77.14 L
Expenditure since inception
₹47.16 L
Balance cost (unspent)
₹29.98 L
Wage ₹25.00 L · Material ₹4.98 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Constr of Cement Concrete Roads
1 works
₹36.05 L sanctioned
₹20.42 L spent (57%)
02
Construction of Trench
1 works
₹14.94 L sanctioned
₹6.42 L spent (43%)
03
Construction of Well
4 works
₹13.07 L sanctioned
₹9.68 L spent (74%)
04
Construction of Bund
1 works
₹10.00 L sanctioned
₹9.22 L spent (92%)
05
Rural Housing
12 works
₹2.82 L sanctioned
₹1.29 L spent (46%)
06
Well Recharge
1 works
₹25,899 sanctioned
₹12,384 spent (48%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)