| Sr. | New Work Type | Ongoing works | Sanctioned | Expenditure | Balance cost | Exp. % |
|---|---|---|---|---|---|---|
| 1 | Rural Housing | 1,781 | 4.79 | 2.15 | 2.63 | 45% |
| 2 | Construction of Well | 180 | 5.87 | 3.54 | 2.33 | 60% |
| 3 | Plantation | 175 | 4.65 | 1.17 | 3.48 | 25% |
| 4 | Construction of Check Dam/Stop Dam | 119 | 10.80 | 6.76 | 4.04 | 63% |
| 5 | Construction of Bund | 104 | 12.09 | 7.54 | 4.55 | 62% |
| 6 | Farm Pond | 66 | 1.46 | 0.66 | 0.80 | 45% |
| 7 | Construction of Trench | 41 | 2.82 | 1.12 | 1.70 | 40% |
| 8 | Constr of Cement Concrete Roads | 24 | 2.87 | 1.82 | 1.04 | 64% |
| 9 | Construction of Percolation Tank | 19 | 1.60 | 0.41 | 1.19 | 26% |
| 10 | Construction of Road and Culvert | 16 | 4.07 | 3.06 | 1.01 | 75% |
| 11 | Construction of Tank | 16 | 3.42 | 1.95 | 1.47 | 57% |
| 12 | Well Recharge | 15 | 0.23 | 0.09 | 0.15 | 37% |
| 13 | Constr of Gabion | 13 | 0.83 | 0.42 | 0.41 | 50% |
| 14 | Solid and Liquid Waste Management | 12 | 0.17 | 0.08 | 0.09 | 49% |
| 15 | Repair & maint of Pond/ Tank | 8 | 0.72 | 0.33 | 0.39 | 46% |
| 16 | Constr of Aganwadi | 8 | 0.26 | 0.06 | 0.19 | 24% |
| 17 | Construction of Embankment | 7 | 1.11 | 0.93 | 0.18 | 84% |
| 18 | Construction of Canal | 7 | 0.56 | 0.40 | 0.16 | 71% |
| 19 | Land Development | 6 | 0.70 | 0.30 | 0.40 | 43% |
| 20 | Construction of Spur | 5 | 0.61 | 0.53 | 0.08 | 87% |
| 21 | Boulder Check/Gully Plug | 5 | 0.29 | 0.13 | 0.16 | 45% |
| 22 | Terracing | 5 | 0.15 | 0.06 | 0.09 | 41% |
| 23 | Constr of GP Bhawan | 5 | 0.31 | 0.12 | 0.19 | 38% |
| 24 | Community Sanitary Complex | 4 | 0.02 | 0.01 | 0.01 | 60% |
| 25 | Construction of NADEP/Vermi Compost Pit | 3 | 0.09 | 0.04 | 0.05 | 42% |
| 26 | Repair & maint of Water Harvesting Structures | 2 | 0.12 | 0.05 | 0.07 | 41% |
| 27 | Construction of Recharge Pits | 2 | 0.01 | 0.00 | 0.00 | 61% |
| 28 | Construction of Crematorium | 2 | 0.05 | 0.05 | 0.01 | 89% |
| 29 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 0.16 | 0.07 | 0.09 | 44% |
| 30 | Construction of building/workshed for SHG | 1 | 0.00 | 0.00 | 0.00 | 68% |
| 31 | Construction of Play field | 1 | 0.10 | 0.08 | 0.02 | 79% |
| 32 | Constr of Kitchen Shed | 1 | 0.00 | 0.00 | 0.00 | 3% |
| 33 | Poultry Shelter | 1 | 0.00 | 0.00 | 0.00 | 0% |
| 34 | Construction of Other Community Building/Assets | 1 | 0.02 | 0.02 | 0.00 | 86% |
| 35 | Goat Shelter | 1 | 0.00 | 0.00 | 0.00 | 92% |
| 36 | Nursery Development | 1 | 0.01 | 0.00 | 0.01 | 2% |
| Total | 2,659 | 60.97 | 33.95 | 27.02 |