Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:49:07.017331
Works ongoing
13
Sanctioned (pure scheme)
₹1.40 Cr
Expenditure since inception
₹1.01 Cr
Balance cost (unspent)
₹38.98 L
Wage ₹31.97 L · Material ₹7.01 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
2 works
₹69.62 L sanctioned
₹51.92 L spent (75%)
02
Constr of Cement Concrete Roads
1 works
₹34.19 L sanctioned
₹28.20 L spent (82%)
03
Construction of Bund
1 works
₹14.45 L sanctioned
₹14.25 L spent (99%)
04
Construction of Well
2 works
₹7.16 L sanctioned
₹3.87 L spent (54%)
05
Well Recharge
1 works
₹5.84 L sanctioned
₹91,308 spent (16%)
06
Plantation
3 works
₹4.84 L sanctioned
₹99,022 spent (20%)
07
Farm Pond
2 works
₹3.58 L sanctioned
₹74,688 spent (21%)
08
Rural Housing
1 works
₹27,000 sanctioned
₹7,830 spent (29%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)