Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:49:07.017331
Works ongoing
39
Sanctioned (pure scheme)
₹1.63 Cr
Expenditure since inception
₹1.44 Cr
Balance cost (unspent)
₹18.70 L
Wage ₹9.13 L · Material ₹9.57 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
5 works
₹74.38 L sanctioned
₹69.70 L spent (94%)
02
Land Development
2 works
₹29.89 L sanctioned
₹28.23 L spent (94%)
03
Construction of Road and Culvert
1 works
₹24.95 L sanctioned
₹24.07 L spent (96%)
04
Construction of Check Dam/Stop Dam
1 works
₹14.93 L sanctioned
₹14.07 L spent (94%)
05
Construction of Well
3 works
₹9.71 L sanctioned
₹4.29 L spent (44%)
06
Rural Housing
26 works
₹7.02 L sanctioned
₹3.41 L spent (49%)
07
Plantation
1 works
₹2.15 L sanctioned
₹55,530 spent (26%)
08
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
0 works
₹0 sanctioned
₹0 spent (0%)