Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
37
Sanctioned (pure scheme)
₹2.93 Cr
Expenditure since inception
₹2.47 Cr
Balance cost (unspent)
₹46.21 L
Wage ₹28.67 L · Material ₹17.54 L
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
6 works
₹89.78 L sanctioned
₹76.56 L spent (85%)
02
Works for Flood Control and Protection
5 works
₹74.46 L sanctioned
₹71.12 L spent (96%)
03
Construction of Check Dam/Stop Dam
4 works
₹69.62 L sanctioned
₹52.35 L spent (75%)
04
Land Development
2 works
₹29.76 L sanctioned
₹28.89 L spent (97%)
05
Construction of Tank
1 works
₹14.95 L sanctioned
₹7.52 L spent (50%)
06
Plantation
2 works
₹10.84 L sanctioned
₹9.10 L spent (84%)
07
Rural Housing
17 works
₹3.99 L sanctioned
₹1.65 L spent (41%)
08
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
10
Constr of Aganwadi
0 works
₹0 sanctioned
₹0 spent (0%)