Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
36
Sanctioned (pure scheme)
₹53.28 L
Expenditure since inception
₹21.82 L
Balance cost (unspent)
₹31.45 L
Wage ₹16.65 L · Material ₹14.81 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
2 works
₹19.91 L sanctioned
₹10.84 L spent (54%)
02
Construction of Check Dam/Stop Dam
3 works
₹14.69 L sanctioned
₹27,144 spent (2%)
03
Construction of Well
2 works
₹5.59 L sanctioned
₹5.32 L spent (95%)
04
Rural Housing
23 works
₹5.40 L sanctioned
₹3.68 L spent (68%)
05
Repair & Maint of Check Dam/Stop Dam
1 works
₹3.33 L sanctioned
₹94,830 spent (29%)
06
Plantation
1 works
₹2.02 L sanctioned
₹68,787 spent (34%)
07
Constr of Cement Concrete Roads
3 works
₹1.67 L sanctioned
₹7,080 spent (4%)
08
Repair & maint of Road
1 works
₹67,000 sanctioned
₹1,224 spent (2%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)