Monitor — Ongoing Works
Rollup last refreshed: 2026-08-19 08:32:20.978731
Works ongoing
23
Sanctioned (pure scheme)
₹1.86 Cr
Expenditure since inception
₹83.70 L
Balance cost (unspent)
₹1.02 Cr
Wage ₹79.85 L · Material ₹22.30 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
4 works
₹48.91 L sanctioned
₹19.19 L spent (39%)
02
Construction of Tank
4 works
₹40.00 L sanctioned
₹20.73 L spent (52%)
03
Construction of Trench
2 works
₹29.79 L sanctioned
₹0 spent (0%)
04
Land Development
5 works
₹24.90 L sanctioned
₹10.91 L spent (44%)
05
Construction of Road and Culvert
1 works
₹15.36 L sanctioned
₹15.06 L spent (98%)
06
Construction of Check Dam/Stop Dam
3 works
₹14.94 L sanctioned
₹14.09 L spent (94%)
07
Plantation
1 works
₹8.01 L sanctioned
₹72,236 spent (9%)
08
Construction of Crematorium
1 works
₹3.47 L sanctioned
₹2.97 L spent (85%)
09
Rural Housing
2 works
₹46,980 sanctioned
₹3,474 spent (7%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)