MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-10-15 06:57:05.982177
to
Reset filters
Works ongoing
2,535
Sanctioned (pure scheme)
₹34.74 Cr
Expenditure since inception
₹16.10 Cr
Balance cost (unspent)
₹18.64 Cr
Wage ₹12.37 Cr · Material ₹6.27 Cr
Expenditure trend
₹62.01 Cr
This Week
₹36.72 Cr
Last Week
▲ 68.9% vs last week
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
  • VIDISHA — LATERI−₹52.78 L
Mandays trend
7,10,772
This Week
12,10,003
Last Week
▼ 41.3%
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
  • MORENA — MORENA0

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
2,004 works
₹5.42 Cr sanctioned
₹2.85 Cr spent (52%)
02
Construction of Bund
54 works
₹5.33 Cr sanctioned
₹2.35 Cr spent (44%)
03
Plantation
144 works
₹3.98 Cr sanctioned
₹77.44 L spent (19%)
04
Construction of Percolation Tank
24 works
₹3.24 Cr sanctioned
₹1.05 Cr spent (32%)
05
Construction of Road and Culvert
13 works
₹2.53 Cr sanctioned
₹1.81 Cr spent (71%)
06
Repair & maint of Pond/ Tank
23 works
₹2.29 Cr sanctioned
₹1.42 Cr spent (62%)
07
Construction of Tank
15 works
₹1.84 Cr sanctioned
₹67.05 L spent (37%)
08
Constr of Cement Concrete Roads
25 works
₹1.75 Cr sanctioned
₹1.10 Cr spent (63%)
09
Construction of Well
60 works
₹1.57 Cr sanctioned
₹81.90 L spent (52%)
10
Construction of Check Dam/Stop Dam
10 works
₹1.24 Cr sanctioned
₹78.34 L spent (63%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 2,004 5.42 2.85 2.58
53%
2 Plantation 144 3.98 0.77 3.20
20%
3 Construction of Well 60 1.57 0.82 0.75
52%
4 Construction of Bund 54 5.33 2.35 2.98
44%
5 Cattle Shed 49 0.98 0.76 0.22
78%
6 Farm Pond 39 0.57 0.07 0.51
12%
7 Constr of Cement Concrete Roads 25 1.75 1.10 0.65
63%
8 Construction of Percolation Tank 24 3.24 1.05 2.19
32%
9 Repair & maint of Pond/ Tank 23 2.29 1.42 0.87
62%
10 Construction of Tank 15 1.84 0.67 1.17
37%
11 Construction of Road and Culvert 13 2.53 1.81 0.72
71%
12 Solid and Liquid Waste Management 13 0.07 0.04 0.03
55%
13 Constr of Gabion 10 0.99 0.39 0.60
40%
14 Construction of Check Dam/Stop Dam 10 1.24 0.78 0.46
63%
15 Land Development 8 0.48 0.25 0.23
52%
16 Construction of NADEP/Vermi Compost Pit 8 0.01 0.00 0.01
19%
17 Construction of Trench 6 0.63 0.08 0.55
13%
18 Constr of Compound wall 5 0.19 0.11 0.08
56%
19 Community Sanitary Complex 5 0.04 0.01 0.02
40%
20 Constr of GP Bhawan 3 0.21 0.03 0.18
14%
21 Repair & Maint of Bund 3 0.31 0.25 0.06
81%
22 Terracing 3 0.18 0.14 0.04
79%
23 Well Recharge 2 0.03 0.02 0.01
65%
24 Nursery Development 2 0.52 0.09 0.43
17%
25 Repair & maint of Percolation Tank 2 0.17 0.11 0.06
64%
26 Construction of Spur 1 0.05 0.04 0.00
94%
27 Other Works 1 0.01 0.00 0.01
23%
28 Constr of Aganwadi 1 0.02 0.00 0.02
3%
29 Piggery Shelter 1 0.00 0.00 0.00
0%
30 Construction of Crematorium 1 0.08 0.08 0.01
93%
Total 2,535 34.74 16.10 18.64
All 30 rows (zero-value rows hidden) ⇩ Export to Excel