Monitor — Ongoing Works
Rollup last refreshed: 2026-10-12 07:04:13.185207
Works ongoing
19
Sanctioned (pure scheme)
₹70.08 L
Expenditure since inception
₹15.88 L
Balance cost (unspent)
₹54.20 L
Wage ₹29.22 L · Material ₹24.98 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
1 works
₹14.96 L sanctioned
₹8.30 L spent (56%)
02
Farm Pond
4 works
₹12.82 L sanctioned
₹5.47 L spent (43%)
03
Boulder Check/Gully Plug
1 works
₹12.58 L sanctioned
₹68,850 spent (5%)
04
Construction of Check Dam/Stop Dam
1 works
₹10.04 L sanctioned
₹10,962 spent (1%)
05
Construction of Road and Culvert
1 works
₹7.80 L sanctioned
₹52,987 spent (7%)
06
Construction of Trench
2 works
₹5.61 L sanctioned
₹884 spent (0%)
07
Plantation
2 works
₹4.31 L sanctioned
₹750 spent (0%)
08
Rural Housing
5 works
₹1.35 L sanctioned
₹43,578 spent (32%)
09
Constr of Cement Concrete Roads
1 works
₹34,000 sanctioned
₹24,089 spent (71%)
10
Well Recharge
1 works
₹25,899 sanctioned
₹8,613 spent (33%)