Rollup last refreshed: 2026-09-01 08:48:19.512575
Works ongoing
16
Sanctioned (pure scheme)
₹93.11 L
Expenditure since inception
₹24.91 L
Balance cost (unspent)
₹68.20 L
Wage ₹22.13 L · Material ₹46.06 L
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
2 works
₹28.36 L sanctioned
₹42,804 spent (2%)
02
Construction of Road and Culvert
1 works
₹19.90 L sanctioned
₹4.47 L spent (22%)
03
Plantation
4 works
₹15.72 L sanctioned
₹9.36 L spent (60%)
04
Construction of Well
2 works
₹7.40 L sanctioned
₹3.91 L spent (53%)
05
Farm Pond
2 works
₹6.57 L sanctioned
₹1.67 L spent (25%)
06
Roof Water Harvesting on gov/panchayat bldg
1 works
₹4.92 L sanctioned
₹1.13 L spent (23%)
07
Construction of Percolation Tank
1 works
₹4.89 L sanctioned
₹1.81 L spent (37%)
08
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
1 works
₹2.93 L sanctioned
₹2 spent (0%)
09
Constr of Cement Concrete Roads
1 works
₹2.19 L sanctioned
₹2.12 L spent (97%)
10
Rural Housing
1 works
₹23,490 sanctioned
₹1,204 spent (5%)