Rollup last refreshed: 2026-07-11 02:05:34.314168
to
Reset filters
Works ongoing
2,415
Sanctioned (pure scheme)
₹28.35 Cr
Expenditure since inception
₹7.42 Cr
Balance cost (unspent)
₹20.93 Cr
Wage ₹10.07 Cr · Material ₹10.86 Cr
Expenditure trend
₹56.93 Cr
This Week
₹182.70 Cr
Last Week
▼ 68.8% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Slowest spending this week — worth a look
  • MORENA — JOURA−₹1.63 Cr
Mandays trend
2,63,410
This Week
21,46,699
Last Week
▼ 87.7%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-35,502

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
92 works
₹7.67 Cr sanctioned
₹22.37 L spent (3%)
02
Rural Housing
1,749 works
₹4.11 Cr sanctioned
₹2.40 Cr spent (59%)
03
Plantation
139 works
₹4.01 Cr sanctioned
₹97.19 L spent (24%)
04
Construction of Tank
29 works
₹1.65 Cr sanctioned
₹35.39 L spent (21%)
05
Farm Pond
89 works
₹1.65 Cr sanctioned
₹33.52 L spent (20%)
06
Construction of Well
39 works
₹1.25 Cr sanctioned
₹40.14 L spent (32%)
07
Construction of Road and Culvert
15 works
₹1.17 Cr sanctioned
₹61.04 L spent (52%)
08
Construction of Crematorium
31 works
₹83.94 L sanctioned
₹32.91 L spent (39%)
09
Land Development
8 works
₹66.51 L sanctioned
₹44.72 L spent (67%)
10
Nursery Development
2 works
₹61.17 L sanctioned
₹12.04 L spent (20%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 1,749 4.11 2.40 1.70
59%
2 Plantation 139 4.01 0.97 3.04
24%
3 Construction of Check Dam/Stop Dam 92 7.67 0.22 7.44
3%
4 Farm Pond 89 1.65 0.34 1.31
20%
5 Constr of Cement Concrete Roads 71 0.54 0.32 0.22
59%
6 Construction of Well 39 1.25 0.40 0.85
32%
7 Construction of Crematorium 31 0.84 0.33 0.51
39%
8 Construction of Tank 29 1.65 0.35 1.29
22%
9 Construction of Bund 27 0.55 0.04 0.52
7%
10 Constr of Aganwadi 22 0.55 0.19 0.36
35%
11 Constr of GP Bhawan 17 0.46 0.17 0.28
38%
12 Construction of Percolation Tank 16 0.53 0.11 0.42
21%
13 Construction of Road and Culvert 15 1.17 0.61 0.56
52%
14 Land Development 8 0.67 0.45 0.22
67%
15 Repair & maint of Pond/ Tank 7 0.28 0.01 0.27
3%
16 Well Recharge 7 0.14 0.04 0.09
32%
17 Construction of Trench 6 0.23 0.04 0.20
15%
18 Construction of Play field 5 0.15 0.05 0.10
31%
19 Community Sanitary Complex 5 0.02 0.02 0.01
75%
20 Culvert 4 0.05 0.04 0.01
75%
21 Construction of Other Community Building/Assets 4 0.16 0.10 0.06
65%
22 Repair & Maint of Check Dam/Stop Dam 4 0.21 0.01 0.21
4%
23 Construction of Recharge Pits 3 0.01 0.00 0.01
18%
24 Construction of NADEP/Vermi Compost Pit 3 0.04 0.00 0.04
9%
25 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 2 0.31 0.00 0.31
0%
26 Nursery Development 2 0.61 0.12 0.49
20%
27 Repair & maint of Percolation Tank 2 0.05 0.01 0.04
24%
28 Solid and Liquid Waste Management 2 0.02 0.01 0.01
67%
29 Terracing 2 0.06 0.00 0.06
3%
30 Constr of Compound wall 2 0.00 0.00 −0.00
122%
31 Constr of Food Grain storage 2 0.10 0.00 0.10
1%
32 Constr of Kitchen Shed 1 0.03 0.03 0.00
87%
33 Poultry Shelter 1 0.03 0.01 0.03
23%
34 Renovation of traditional water bodies 1 0.01 0.00 0.01
0%
35 Bio-gas plant 1 0.03 0.00 0.03
4%
36 Repair & Maint of Community infrastructure 1 0.00 0.00 0.00
1%
37 Repair & maint of Water Harvesting Structures 1 0.02 0.00 0.02
4%
38 Constr of Gabion 1 0.02 0.00 0.02
13%
39 Grass Land Development 1 0.08 0.01 0.07
13%
40 Boulder Check/Gully Plug 1 0.03 0.01 0.02
29%
Total 2,415 28.35 7.42 20.93