Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
21
Sanctioned (pure scheme)
₹24.72 L
Expenditure since inception
₹3.09 L
Balance cost (unspent)
₹21.63 L
Wage ₹11.36 L · Material ₹10.27 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹11.50 L sanctioned
₹5,216 spent (0%)
02
Construction of Tank
1 works
₹7.31 L sanctioned
₹11,736 spent (2%)
03
Rural Housing
15 works
₹3.52 L sanctioned
₹2.22 L spent (63%)
04
Constr of Compound wall
1 works
₹88,000 sanctioned
₹42,282 spent (48%)
05
Construction of Bund
1 works
₹59,494 sanctioned
₹180 spent (0%)
06
Farm Pond
1 works
₹50,957 sanctioned
₹3,740 spent (7%)
07
Construction of NADEP/Vermi Compost Pit
1 works
₹40,000 sanctioned
₹23,719 spent (59%)
08
Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
09
Land Development
0 works
₹0 sanctioned
₹0 spent (0%)
10
Plantation
0 works
₹0 sanctioned
₹0 spent (0%)