Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
19
Sanctioned (pure scheme)
₹23.01 L
Expenditure since inception
₹5.26 L
Balance cost (unspent)
₹17.75 L
Wage ₹6.69 L · Material ₹11.06 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹11.30 L sanctioned
₹330 spent (0%)
02
Plantation
3 works
₹3.91 L sanctioned
₹1.25 L spent (32%)
03
Farm Pond
1 works
₹3.86 L sanctioned
₹1.39 L spent (36%)
04
Rural Housing
11 works
₹2.54 L sanctioned
₹2.34 L spent (92%)
05
Construction of Bund
1 works
₹57,000 sanctioned
₹362 spent (1%)
06
Cattle Shed
1 works
₹51,000 sanctioned
₹11,847 spent (23%)
07
Solid and Liquid Waste Management
1 works
₹32,000 sanctioned
₹14,487 spent (45%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)