Monitor — Ongoing Works
Rollup last refreshed: 2026-08-19 08:32:20.978731
Works ongoing
81
Sanctioned (pure scheme)
₹2.49 Cr
Expenditure since inception
₹1.25 Cr
Balance cost (unspent)
₹1.25 Cr
Wage ₹56.38 L · Material ₹68.55 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Cattle Shed
4 works
₹1.52 Cr sanctioned
₹1.05 Cr spent (69%)
02
Grass Land Development
2 works
₹29.89 L sanctioned
₹55,736 spent (2%)
03
Rural Housing
65 works
₹15.27 L sanctioned
₹7.34 L spent (48%)
04
Construction of Bund
1 works
₹14.99 L sanctioned
₹23,940 spent (2%)
05
Construction of Trench
1 works
₹14.51 L sanctioned
₹5.32 L spent (37%)
06
Construction of Check Dam/Stop Dam
1 works
₹6.73 L sanctioned
₹1.70 L spent (25%)
07
Repair & maint of Pond/ Tank
1 works
₹5.55 L sanctioned
₹78,300 spent (14%)
08
Farm Pond
1 works
₹4.51 L sanctioned
₹96,107 spent (21%)
09
Construction of Well
1 works
₹2.00 L sanctioned
₹1.30 L spent (65%)
10
Plantation
1 works
₹1.53 L sanctioned
₹78,138 spent (51%)