Monitor — Ongoing Works
Rollup last refreshed: 2026-10-19 07:04:39.053416
Works ongoing
18
Sanctioned (pure scheme)
₹32.02 L
Expenditure since inception
₹14.72 L
Balance cost (unspent)
₹17.30 L
Wage ₹9.40 L · Material ₹7.90 L
Expenditure trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Slowest spending this week — worth a look
Mandays trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Farm Pond
4 works
₹13.76 L sanctioned
₹6.49 L spent (47%)
02
Construction of Check Dam/Stop Dam
2 works
₹6.53 L sanctioned
₹4.33 L spent (66%)
03
Culvert
1 works
₹3.95 L sanctioned
₹4,560 spent (1%)
04
Constr of Cement Concrete Roads
2 works
₹2.64 L sanctioned
₹59,940 spent (23%)
05
Cattle Shed
2 works
₹2.04 L sanctioned
₹1.97 L spent (97%)
06
Rural Housing
2 works
₹1.30 L sanctioned
₹96,697 spent (75%)
07
Constr of GP Bhawan
1 works
₹59,000 sanctioned
₹3,762 spent (6%)
08
Land Development
1 works
₹57,072 sanctioned
₹6,948 spent (12%)
09
Construction of NADEP/Vermi Compost Pit
1 works
₹36,000 sanctioned
₹16,212 spent (45%)
10
Solid and Liquid Waste Management
2 works
₹28,568 sanctioned
₹5,700 spent (20%)