Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:36:19.743515
Works ongoing
21
Sanctioned (pure scheme)
₹22.59 L
Expenditure since inception
₹5.21 L
Balance cost (unspent)
₹17.38 L
Wage ₹14.81 L · Material ₹2.56 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Slowest spending this week — worth a look
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
1 works
₹9.87 L sanctioned
₹1.01 L spent (10%)
02
Construction of Bund
1 works
₹3.52 L sanctioned
₹52,998 spent (15%)
03
Rural Housing
14 works
₹3.29 L sanctioned
₹1.89 L spent (57%)
04
Construction of Check Dam/Stop Dam
1 works
₹2.63 L sanctioned
₹74,640 spent (28%)
05
Constr of Compound wall
1 works
₹1.46 L sanctioned
₹442 spent (0%)
06
Community Sanitary Complex
1 works
₹1.00 L sanctioned
₹52,609 spent (53%)
07
Culvert
2 works
₹82,200 sanctioned
₹50,412 spent (61%)
08
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Well
0 works
₹0 sanctioned
₹0 spent (0%)
10
Farm Pond
0 works
₹0 sanctioned
₹0 spent (0%)