Monitor — Ongoing Works
Rollup last refreshed: 2026-08-26 17:54:53.293656
Works ongoing
7
Sanctioned (pure scheme)
₹38.76 L
Expenditure since inception
₹6.61 L
Balance cost (unspent)
₹32.15 L
Wage ₹22.21 L · Material ₹9.94 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
5 works
₹30.65 L sanctioned
₹4.50 L spent (15%)
02
Roof Water Harvesting on gov/panchayat bldg
1 works
₹6.06 L sanctioned
₹2.10 L spent (35%)
03
Construction of Percolation Tank
1 works
₹2.05 L sanctioned
₹1,330 spent (1%)
04
Constr of Compound wall
0 works
₹0 sanctioned
₹0 spent (0%)
05
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)