Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
26
Sanctioned (pure scheme)
₹49.63 L
Expenditure since inception
₹36.94 L
Balance cost (unspent)
₹12.69 L
Wage ₹8.46 L · Material ₹4.24 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Cattle Shed
1 works
₹38.04 L sanctioned
₹33.66 L spent (88%)
02
Farm Pond
3 works
₹5.97 L sanctioned
₹12,497 spent (2%)
03
Rural Housing
21 works
₹5.19 L sanctioned
₹2.92 L spent (56%)
04
Community Sanitary Complex
1 works
₹43,000 sanctioned
₹23,600 spent (55%)
05
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)