Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:36:19.743515
Works ongoing
11
Sanctioned (pure scheme)
₹31.02 L
Expenditure since inception
₹11.06 L
Balance cost (unspent)
₹19.96 L
Wage ₹10.63 L · Material ₹9.33 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Slowest spending this week — worth a look
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
5 works
₹14.03 L sanctioned
₹4.45 L spent (32%)
02
Construction of Well
3 works
₹9.02 L sanctioned
₹5.14 L spent (57%)
03
Construction of Tank
1 works
₹4.93 L sanctioned
₹1.09 L spent (22%)
04
Construction of Trench
1 works
₹2.79 L sanctioned
₹29,533 spent (11%)
05
Rural Housing
1 works
₹24,795 sanctioned
₹8,884 spent (36%)
06
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)