Monitor — Ongoing Works
Rollup last refreshed: 2026-08-26 17:54:53.293656
Works ongoing
26
Sanctioned (pure scheme)
₹59.25 L
Expenditure since inception
₹25.61 L
Balance cost (unspent)
₹33.64 L
Wage ₹15.78 L · Material ₹17.86 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
3 works
₹29.71 L sanctioned
₹15.42 L spent (52%)
02
Construction of Well
4 works
₹10.73 L sanctioned
₹3.14 L spent (29%)
03
Plantation
5 works
₹8.97 L sanctioned
₹2.03 L spent (23%)
04
Well Recharge
1 works
₹2.75 L sanctioned
₹99,940 spent (36%)
05
Boulder Check/Gully Plug
1 works
₹2.48 L sanctioned
₹72,478 spent (29%)
06
Rural Housing
10 works
₹2.23 L sanctioned
₹1.55 L spent (69%)
07
Constr of Cement Concrete Roads
1 works
₹1.22 L sanctioned
₹92,059 spent (75%)
08
Construction of Trench
1 works
₹1.15 L sanctioned
₹82,029 spent (71%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)