Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
97
Sanctioned (pure scheme)
₹92.18 L
Expenditure since inception
₹45.23 L
Balance cost (unspent)
₹46.94 L
Wage ₹22.59 L · Material ₹24.35 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
26 works
₹54.37 L sanctioned
₹22.61 L spent (42%)
02
Rural Housing
61 works
₹14.33 L sanctioned
₹11.44 L spent (80%)
03
Well Recharge
3 works
₹9.85 L sanctioned
₹4.69 L spent (48%)
04
Construction of Well
1 works
₹6.76 L sanctioned
₹4.34 L spent (64%)
05
Construction of Bund
1 works
₹3.33 L sanctioned
₹190 spent (0%)
06
Constr of Cement Concrete Roads
2 works
₹1.85 L sanctioned
₹1.68 L spent (91%)
07
Construction of Percolation Tank
2 works
₹1.12 L sanctioned
₹14,355 spent (13%)
08
Farm Pond
1 works
₹55,865 sanctioned
₹32,625 spent (58%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)