Monitor — Ongoing Works
Rollup last refreshed: 2026-08-19 08:32:20.978731
Works ongoing
78
Sanctioned (pure scheme)
₹1.72 Cr
Expenditure since inception
₹79.36 L
Balance cost (unspent)
₹92.39 L
Wage ₹55.55 L · Material ₹36.84 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
36 works
₹1.15 Cr sanctioned
₹38.76 L spent (34%)
02
Construction of Tank
2 works
₹16.43 L sanctioned
₹13.51 L spent (82%)
03
Construction of Percolation Tank
4 works
₹14.84 L sanctioned
₹7.03 L spent (47%)
04
Construction of Well
1 works
₹5.71 L sanctioned
₹4.83 L spent (85%)
05
Rural Housing
24 works
₹5.61 L sanctioned
₹5.14 L spent (92%)
06
Works for Flood Control and Protection
1 works
₹3.85 L sanctioned
₹3.27 L spent (85%)
07
Construction of Check Dam/Stop Dam
1 works
₹3.55 L sanctioned
₹94,221 spent (27%)
08
Construction of Road and Culvert
3 works
₹2.68 L sanctioned
₹2.34 L spent (87%)
09
Culvert
1 works
₹2.25 L sanctioned
₹2.22 L spent (99%)
10
Constr of Cement Concrete Roads
3 works
₹1.67 L sanctioned
₹1.10 L spent (66%)