Monitor — Ongoing Works
Rollup last refreshed: 2026-10-15 06:45:09.438671
Works ongoing
64
Sanctioned (pure scheme)
₹1.50 Cr
Expenditure since inception
₹5.74 L
Balance cost (unspent)
₹1.44 Cr
Wage ₹1.02 Cr · Material ₹42.84 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- SHIVPURI — KOLARAS−₹34,632
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
16 works
₹51.75 L sanctioned
₹4.98 L spent (10%)
02
Farm Pond
9 works
₹31.49 L sanctioned
₹0 spent (0%)
03
Grass Land Development
1 works
₹14.99 L sanctioned
₹0 spent (0%)
04
Construction of Road and Culvert
1 works
₹12.77 L sanctioned
₹0 spent (0%)
05
Construction of Tank
2 works
₹12.69 L sanctioned
₹0 spent (0%)
06
Rural Housing
24 works
₹6.48 L sanctioned
₹76,500 spent (12%)
07
Construction of Percolation Tank
4 works
₹5.61 L sanctioned
₹0 spent (0%)
08
Construction of Play field
1 works
₹5.03 L sanctioned
₹0 spent (0%)
09
Community Sanitary Complex
2 works
₹4.78 L sanctioned
₹0 spent (0%)
10
Construction of Check Dam/Stop Dam
1 works
₹4.15 L sanctioned
₹0 spent (0%)