Monitor — Ongoing Works
Rollup last refreshed: 2026-08-25 08:55:11.826995
Works ongoing
15
Sanctioned (pure scheme)
₹3.47 L
Expenditure since inception
₹2.37 L
Balance cost (unspent)
₹1.10 L
Wage ₹1.10 L · Material ₹0
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
13 works
₹3.05 L sanctioned
₹2.15 L spent (70%)
02
Constr of Cement Concrete Roads
2 works
₹42,000 sanctioned
₹22,020 spent (52%)
03
Constr of Aganwadi
0 works
₹0 sanctioned
₹0 spent (0%)
04
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
05
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Trench
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Well
0 works
₹0 sanctioned
₹0 spent (0%)
09
Farm Pond
0 works
₹0 sanctioned
₹0 spent (0%)
10
Land Development
0 works
₹0 sanctioned
₹0 spent (0%)