Monitor — Ongoing Works
Rollup last refreshed: 2026-09-07 07:03:15.513604
Works ongoing
27
Sanctioned (pure scheme)
₹54.06 L
Expenditure since inception
₹28.44 L
Balance cost (unspent)
₹25.63 L
Wage ₹13.08 L · Material ₹12.55 L
Expenditure trend
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
Mandays trend
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Percolation Tank
1 works
₹22.93 L sanctioned
₹18.07 L spent (79%)
02
Well Recharge
3 works
₹12.69 L sanctioned
₹5.33 L spent (42%)
03
Construction of Well
2 works
₹7.49 L sanctioned
₹3.13 L spent (42%)
04
Plantation
2 works
₹6.22 L sanctioned
₹70,213 spent (11%)
05
Rural Housing
12 works
₹3.24 L sanctioned
₹1.01 L spent (31%)
06
Community Sanitary Complex
1 works
₹1.03 L sanctioned
₹20,604 spent (20%)
07
Construction of Check Dam/Stop Dam
6 works
₹46,100 sanctioned
₹0 spent (0%)
08
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
09
Cattle Shed
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)