Monitor — Ongoing Works

Rollup last refreshed: 2026-08-27 14:06:46.546602
to
Reset filters
Works ongoing
1,971
Sanctioned (pure scheme)
₹45.59 Cr
Expenditure since inception
₹23.01 Cr
Balance cost (unspent)
₹22.58 Cr
Wage ₹11.64 Cr · Material ₹10.94 Cr
Expenditure trend
−₹1.49 Cr
This Week
−₹1.47 Cr
Last Week
▼ 1.6% vs last week
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹90.28 L
Mandays trend
-94,475
This Week
-1,36,226
Last Week
▲ 30.6%
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-53,337

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Well Recharge
242 works
₹8.30 Cr sanctioned
₹3.68 Cr spent (44%)
02
Construction of Tank
34 works
₹6.98 Cr sanctioned
₹3.58 Cr spent (51%)
03
Construction of Well
186 works
₹5.83 Cr sanctioned
₹2.83 Cr spent (48%)
04
Plantation
232 works
₹5.77 Cr sanctioned
₹1.48 Cr spent (26%)
05
Farm Pond
138 works
₹3.87 Cr sanctioned
₹1.86 Cr spent (48%)
06
Construction of Road and Culvert
21 works
₹3.43 Cr sanctioned
₹2.65 Cr spent (77%)
07
Construction of Check Dam/Stop Dam
25 works
₹3.23 Cr sanctioned
₹1.93 Cr spent (60%)
08
Rural Housing
993 works
₹2.33 Cr sanctioned
₹1.37 Cr spent (59%)
09
Culvert
18 works
₹2.28 Cr sanctioned
₹1.74 Cr spent (76%)
10
Construction of Percolation Tank
20 works
₹1.90 Cr sanctioned
₹1.17 Cr spent (61%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 993 2.33 1.37 0.96
59%
2 Well Recharge 242 8.30 3.68 4.62
44%
3 Plantation 232 5.77 1.48 4.29
26%
4 Construction of Well 186 5.83 2.83 3.00
49%
5 Farm Pond 138 3.87 1.86 2.01
48%
6 Construction of Tank 34 6.98 3.58 3.40
51%
7 Construction of Check Dam/Stop Dam 25 3.23 1.93 1.29
60%
8 Construction of Road and Culvert 21 3.43 2.65 0.77
78%
9 Construction of Percolation Tank 20 1.90 1.17 0.73
61%
10 Culvert 18 2.28 1.74 0.55
76%
11 Construction of Recharge Pits 9 0.02 0.00 0.01
27%
12 Repair & maint of Pond/ Tank 7 0.12 0.00 0.11
1%
13 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 6 0.01 0.00 0.01
0%
14 Constr of GP Bhawan 5 0.40 0.24 0.15
62%
15 Community Sanitary Complex 4 0.04 0.01 0.03
34%
16 Construction of Bund 4 0.19 0.03 0.16
15%
17 Cattle Shed 4 0.04 0.02 0.02
46%
18 Constr of Cement Concrete Roads 4 0.02 0.01 0.00
78%
19 Constr of Compound wall 4 0.39 0.25 0.13
65%
20 Construction of Play field 3 0.14 0.09 0.05
66%
21 Constr of Aganwadi 3 0.09 0.02 0.07
19%
22 Land Development 2 0.02 0.00 0.02
2%
23 Construction of Other Community Building/Assets 2 0.13 0.00 0.12
3%
24 Goat Shelter 1 0.00 0.00 0.00
100%
25 Construction of Crematorium 1 0.02 0.00 0.02
3%
26 Construction of NADEP/Vermi Compost Pit 1 0.00 0.00 0.00
97%
27 Poultry Shelter 1 0.01 0.00 0.00
88%
28 Repair & maint of Percolation Tank 1 0.04 0.02 0.03
36%
Total 1,971 45.59 23.01 22.58
All 28 rows (zero-value rows hidden) ⇩ Export to Excel