Monitor — Ongoing Works
Rollup last refreshed: 2026-10-14 07:05:44.899714
Works ongoing
62
Sanctioned (pure scheme)
₹95.86 L
Expenditure since inception
₹61.30 L
Balance cost (unspent)
₹34.56 L
Wage ₹21.30 L · Material ₹13.26 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- SHIVPURI — KOLARAS−₹34,632
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹49.84 L sanctioned
₹47.22 L spent (95%)
02
Construction of Bund
1 works
₹14.06 L sanctioned
₹663 spent (0%)
03
Rural Housing
44 works
₹11.88 L sanctioned
₹6.98 L spent (59%)
04
Construction of Well
4 works
₹9.91 L sanctioned
₹2.18 L spent (22%)
05
Constr of Aganwadi
1 works
₹5.00 L sanctioned
₹4.71 L spent (94%)
06
Farm Pond
5 works
₹2.79 L sanctioned
₹9,135 spent (3%)
07
Poultry Shelter
2 works
₹1.03 L sanctioned
₹2,280 spent (2%)
08
Well Recharge
3 works
₹77,698 sanctioned
₹5,481 spent (7%)
09
Plantation
1 works
₹55,847 sanctioned
₹2,978 spent (5%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)