Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
42
Sanctioned (pure scheme)
₹67.14 L
Expenditure since inception
₹47.46 L
Balance cost (unspent)
₹19.68 L
Wage ₹11.94 L · Material ₹7.74 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹37.85 L sanctioned
₹37.17 L spent (98%)
02
Plantation
3 works
₹17.20 L sanctioned
₹3.88 L spent (23%)
03
Rural Housing
36 works
₹8.46 L sanctioned
₹5.44 L spent (64%)
04
Farm Pond
1 works
₹3.38 L sanctioned
₹96,708 spent (29%)
05
Well Recharge
1 works
₹25,899 sanctioned
₹261 spent (1%)
06
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
07
Constr of Kitchen Shed
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of building/workshed for SHG
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)