Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:36:19.743515
Works ongoing
102
Sanctioned (pure scheme)
₹2.17 Cr
Expenditure since inception
₹1.34 Cr
Balance cost (unspent)
₹82.94 L
Wage ₹52.99 L · Material ₹29.95 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Slowest spending this week — worth a look
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Constr of Cement Concrete Roads
1 works
₹96.34 L sanctioned
₹82.98 L spent (86%)
02
Construction of Check Dam/Stop Dam
1 works
₹45.32 L sanctioned
₹3.36 L spent (7%)
03
Plantation
13 works
₹26.46 L sanctioned
₹17.65 L spent (67%)
04
Construction of Well
6 works
₹20.89 L sanctioned
₹11.90 L spent (57%)
05
Rural Housing
78 works
₹18.26 L sanctioned
₹11.43 L spent (63%)
06
Construction of Tank
2 works
₹9.59 L sanctioned
₹6.79 L spent (71%)
07
Constr of GP Bhawan
1 works
₹25,451 sanctioned
₹6,769 spent (27%)
08
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)