Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
38
Sanctioned (pure scheme)
₹25.25 L
Expenditure since inception
₹18.96 L
Balance cost (unspent)
₹6.29 L
Wage ₹4.13 L · Material ₹2.16 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
33 works
₹7.70 L sanctioned
₹7.23 L spent (94%)
02
Constr of Compound wall
1 works
₹5.35 L sanctioned
₹4.29 L spent (80%)
03
Constr of Aganwadi
1 works
₹5.00 L sanctioned
₹4.90 L spent (98%)
04
Construction of Tank
1 works
₹3.97 L sanctioned
₹96,090 spent (24%)
05
Plantation
1 works
₹2.25 L sanctioned
₹1.56 L spent (69%)
06
Construction of NADEP/Vermi Compost Pit
1 works
₹97,811 sanctioned
₹2,702 spent (3%)
07
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)