Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:36:19.743515
Works ongoing
25
Sanctioned (pure scheme)
₹72.23 L
Expenditure since inception
₹25.86 L
Balance cost (unspent)
₹46.37 L
Wage ₹18.79 L · Material ₹27.58 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Slowest spending this week — worth a look
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
7 works
₹21.46 L sanctioned
₹7.22 L spent (34%)
02
Repair & maint of Water Harvesting Structures
1 works
₹14.95 L sanctioned
₹1.14 L spent (8%)
03
Construction of Road and Culvert
1 works
₹14.30 L sanctioned
₹13.22 L spent (92%)
04
Construction of Check Dam/Stop Dam
2 works
₹4.52 L sanctioned
₹19,980 spent (4%)
05
Boulder Check/Gully Plug
2 works
₹3.96 L sanctioned
₹69,712 spent (18%)
06
Community Sanitary Complex
1 works
₹3.26 L sanctioned
₹34,272 spent (11%)
07
Constr of Gabion
1 works
₹3.07 L sanctioned
₹11,580 spent (4%)
08
Farm Pond
2 works
₹2.40 L sanctioned
₹1.27 L spent (53%)
09
Plantation
1 works
₹2.13 L sanctioned
₹79,933 spent (37%)
10
Well Recharge
6 works
₹1.55 L sanctioned
₹83,714 spent (54%)