Monitor — Ongoing Works
Rollup last refreshed: 2026-10-17 07:04:51.670761
Works ongoing
48
Sanctioned (pure scheme)
₹2.29 Cr
Expenditure since inception
₹69.02 L
Balance cost (unspent)
₹1.60 Cr
Wage ₹91.40 L · Material ₹69.07 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
21 works
₹1.15 Cr sanctioned
₹31.74 L spent (28%)
02
Construction of Tank
4 works
₹46.49 L sanctioned
₹18.86 L spent (41%)
03
Construction of Check Dam/Stop Dam
1 works
₹35.89 L sanctioned
₹45,990 spent (1%)
04
Constr of Gabion
2 works
₹9.12 L sanctioned
₹4.29 L spent (47%)
05
Construction of Well
2 works
₹5.14 L sanctioned
₹2.35 L spent (46%)
06
Solid and Liquid Waste Management
3 works
₹4.56 L sanctioned
₹3.51 L spent (77%)
07
Construction of Trench
1 works
₹4.21 L sanctioned
₹1.97 L spent (47%)
08
Construction of Percolation Tank
1 works
₹2.84 L sanctioned
₹2.26 L spent (80%)
09
Farm Pond
4 works
₹2.23 L sanctioned
₹1.02 L spent (46%)
10
Cattle Shed
2 works
₹2.07 L sanctioned
₹1.69 L spent (82%)