MGNREGA Works Dashboard
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
Reset filters
Works ongoing
2,087
Sanctioned (pure scheme)
₹41.94 Cr
Expenditure since inception
₹22.32 Cr
Balance cost (unspent)
₹19.63 Cr
Wage ₹9.97 Cr · Material ₹9.66 Cr
Expenditure trend
₹1.61 Cr
This Week
₹56.93 Cr
Last Week
▼ 97.2% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹58.03 L
Mandays trend
-59,789
This Week
2,63,410
Last Week
▼ 122.7%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-35,508

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
41 works
₹10.26 Cr sanctioned
₹8.04 Cr spent (78%)
02
Plantation
185 works
₹6.05 Cr sanctioned
₹1.40 Cr spent (23%)
03
Construction of Percolation Tank
44 works
₹6.01 Cr sanctioned
₹1.84 Cr spent (31%)
04
Construction of Well
189 works
₹4.88 Cr sanctioned
₹1.92 Cr spent (39%)
05
Rural Housing
1,348 works
₹3.16 Cr sanctioned
₹1.99 Cr spent (63%)
06
Construction of Road and Culvert
15 works
₹2.59 Cr sanctioned
₹2.17 Cr spent (84%)
07
Construction of Tank
20 works
₹1.92 Cr sanctioned
₹1.14 Cr spent (59%)
08
Terracing
16 works
₹1.63 Cr sanctioned
₹95.91 L spent (59%)
09
Constr of Cement Concrete Roads
4 works
₹1.18 Cr sanctioned
₹94.35 L spent (80%)
10
Farm Pond
62 works
₹91.53 L sanctioned
₹31.63 L spent (35%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 1,348 3.16 1.99 1.18
63%
2 Construction of Well 189 4.88 1.92 2.96
39%
3 Plantation 185 6.05 1.40 4.65
23%
4 Farm Pond 62 0.92 0.32 0.60
35%
5 Construction of Percolation Tank 44 6.01 1.84 4.17
31%
6 Construction of Check Dam/Stop Dam 41 10.26 8.04 2.22
78%
7 Well Recharge 38 0.30 0.06 0.24
20%
8 Cattle Shed 25 0.65 0.47 0.18
73%
9 Solid and Liquid Waste Management 23 0.25 0.14 0.11
56%
10 Construction of Tank 20 1.92 1.14 0.78
59%
11 Terracing 16 1.63 0.96 0.67
59%
12 Construction of Road and Culvert 15 2.59 2.17 0.42
84%
13 Construction of Trench 14 0.33 0.10 0.23
31%
14 Construction of NADEP/Vermi Compost Pit 11 0.08 0.04 0.04
49%
15 Construction of Recharge Pits 10 0.10 0.02 0.08
22%
16 Land Development 6 0.12 0.07 0.06
54%
17 Constr of Compound wall 5 0.42 0.28 0.14
66%
18 Construction of Bund 4 0.02 0.00 0.02
7%
19 Constr of Cement Concrete Roads 4 1.18 0.94 0.23
80%
20 Constr of GP Bhawan 4 0.14 0.09 0.06
60%
21 Constr of Aganwadi 3 0.20 0.04 0.16
20%
22 Community Sanitary Complex 3 0.01 0.01 0.00
73%
23 Goat Shelter 3 0.02 0.02 0.01
65%
24 Construction of Toilets 2 0.01 0.01 0.00
70%
25 Constr of Kitchen Shed 2 0.01 0.01 0.00
68%
26 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.09 0.04 0.05
46%
27 Repair & maint of Water Harvesting Structures 1 0.14 0.13 0.01
96%
28 Constr of Food Grain storage 1 0.00 0.00 0.00
11%
29 Culvert 1 0.03 0.02 0.01
61%
30 Boulder Check/Gully Plug 1 0.00 0.00 −0.00
133%
31 Construction of Canal 1 0.06 0.02 0.04
35%
32 Repair & Maint of Bund 1 0.08 0.00 0.08
0%
33 Repair & Maint of Community infrastructure 1 0.13 0.02 0.11
14%
34 Repair & maint of Percolation Tank 1 0.15 0.03 0.12
19%
35 Repair & maint of Pond/ Tank 1 0.00 0.00 0.00
29%
Total 2,087 41.94 22.32 19.63
All 35 rows (zero-value rows hidden) ⇩ Export to Excel