Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
89
Sanctioned (pure scheme)
₹1.64 Cr
Expenditure since inception
₹89.28 L
Balance cost (unspent)
₹74.89 L
Wage ₹31.85 L · Material ₹43.03 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
30 works
₹68.11 L sanctioned
₹28.86 L spent (42%)
02
Plantation
17 works
₹28.67 L sanctioned
₹20.40 L spent (71%)
03
Construction of Check Dam/Stop Dam
3 works
₹25.01 L sanctioned
₹16.83 L spent (67%)
04
Cattle Shed
11 works
₹12.03 L sanctioned
₹5.21 L spent (43%)
05
Construction of Road and Culvert
1 works
₹11.00 L sanctioned
₹9.60 L spent (87%)
06
Construction of Trench
2 works
₹6.51 L sanctioned
₹47,671 spent (7%)
07
Constr of Aganwadi
1 works
₹5.00 L sanctioned
₹4.96 L spent (99%)
08
Rural Housing
16 works
₹3.76 L sanctioned
₹2.41 L spent (64%)
09
Construction of Bund
5 works
₹3.15 L sanctioned
₹38,560 spent (12%)
10
Land Development
3 works
₹93,387 sanctioned
₹15,015 spent (16%)