Works ongoing
45
Sanctioned (pure scheme)
₹79.14 L
Expenditure since inception
₹52.46 L
Balance cost (unspent)
₹26.67 L
Wage ₹11.02 L · Material ₹15.65 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
3 works
₹35.27 L sanctioned
₹25.84 L spent (73%)
02
Plantation
6 works
₹11.48 L sanctioned
₹9.79 L spent (85%)
03
Construction of Well
4 works
₹8.00 L sanctioned
₹5.50 L spent (69%)
04
Well Recharge
10 works
₹7.68 L sanctioned
₹4.67 L spent (61%)
05
Construction of Trench
1 works
₹5.00 L sanctioned
₹2.45 L spent (49%)
06
Farm Pond
3 works
₹4.43 L sanctioned
₹2.65 L spent (60%)
07
Poultry Shelter
4 works
₹2.06 L sanctioned
₹21,280 spent (10%)
08
Rural Housing
8 works
₹1.88 L sanctioned
₹66,294 spent (35%)
09
Goat Shelter
3 works
₹1.40 L sanctioned
₹20,710 spent (15%)
10
Construction of Bund
2 works
₹1.04 L sanctioned
₹38,448 spent (37%)