Monitor — Ongoing Works
Rollup last refreshed: 2026-09-01 06:53:10.447219
Works ongoing
8
Sanctioned (pure scheme)
₹4.25 L
Expenditure since inception
₹21,000
Balance cost (unspent)
₹4.04 L
Wage ₹3.11 L · Material ₹92,783
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
- ALIRAJPUR — KATTHIWADA-546
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
6 works
₹1.62 L sanctioned
₹8,400 spent (5%)
02
Plantation
1 works
₹1.33 L sanctioned
₹12,600 spent (9%)
03
Community Sanitary Complex
1 works
₹1.30 L sanctioned
₹0 spent (0%)
04
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
05
Solid and Liquid Waste Management
0 works
₹0 sanctioned
₹0 spent (0%)