Monitor — Ongoing Works
Rollup last refreshed: 2026-08-25 08:55:11.826995
Works ongoing
10
Sanctioned (pure scheme)
₹28.60 L
Expenditure since inception
₹4.04 L
Balance cost (unspent)
₹24.56 L
Wage ₹11.53 L · Material ₹13.02 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
1 works
₹12.86 L sanctioned
₹3,876 spent (0%)
02
Plantation
4 works
₹8.63 L sanctioned
₹22,615 spent (3%)
03
Construction of Well
2 works
₹5.06 L sanctioned
₹2.47 L spent (49%)
04
Construction of Check Dam/Stop Dam
1 works
₹1.50 L sanctioned
₹1.18 L spent (79%)
05
Solid and Liquid Waste Management
2 works
₹54,419 sanctioned
₹13,050 spent (24%)
06
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)