Rollup last refreshed: 2026-08-26 17:54:53.293656
Works ongoing
21
Sanctioned (pure scheme)
₹65.79 L
Expenditure since inception
₹39.54 L
Balance cost (unspent)
₹26.26 L
Wage ₹12.45 L · Material ₹13.81 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹29.75 L sanctioned
₹23.74 L spent (80%)
02
Construction of Check Dam/Stop Dam
1 works
₹16.51 L sanctioned
₹4.98 L spent (30%)
03
Construction of Well
3 works
₹7.70 L sanctioned
₹3.19 L spent (41%)
04
Solid and Liquid Waste Management
2 works
₹6.60 L sanctioned
₹5.89 L spent (89%)
05
Rural Housing
11 works
₹2.57 L sanctioned
₹1.56 L spent (61%)
06
Plantation
1 works
₹1.97 L sanctioned
₹1,827 spent (1%)
07
Community Sanitary Complex
1 works
₹70,000 sanctioned
₹14,355 spent (21%)
08
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Fish Drying Infrastructure
0 works
₹0 sanctioned
₹0 spent (0%)