Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 06:52:44.456709
Works ongoing
40
Sanctioned (pure scheme)
₹1.29 Cr
Expenditure since inception
₹10.33 L
Balance cost (unspent)
₹1.18 Cr
Wage ₹73.62 L · Material ₹44.71 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
4 works
₹42.03 L sanctioned
₹4.49 L spent (11%)
02
Plantation
6 works
₹31.43 L sanctioned
₹0 spent (0%)
03
Construction of Well
6 works
₹19.93 L sanctioned
₹1.85 L spent (9%)
04
Construction of Road and Culvert
1 works
₹14.59 L sanctioned
₹2.63 L spent (18%)
05
Construction of Check Dam/Stop Dam
5 works
₹11.75 L sanctioned
₹1,200 spent (0%)
06
Rural Housing
15 works
₹4.05 L sanctioned
₹51,300 spent (13%)
07
Construction of Trench
2 works
₹3.40 L sanctioned
₹82,800 spent (24%)
08
Construction of Percolation Tank
1 works
₹1.48 L sanctioned
₹0 spent (0%)
09
Community Sanitary Complex
0 works
₹0 sanctioned
₹0 spent (0%)
10
Farm Pond
0 works
₹0 sanctioned
₹0 spent (0%)