Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
55
Sanctioned (pure scheme)
₹37.21 L
Expenditure since inception
₹18.06 L
Balance cost (unspent)
₹19.15 L
Wage ₹18.53 L · Material ₹62,204
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹23.83 L sanctioned
₹8.40 L spent (35%)
02
Rural Housing
51 works
₹11.98 L sanctioned
₹8.94 L spent (75%)
03
Constr of Cement Concrete Roads
1 works
₹89,550 sanctioned
₹25,506 spent (28%)
04
Community Sanitary Complex
1 works
₹50,000 sanctioned
₹46,429 spent (93%)
05
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Embankment
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Trench
0 works
₹0 sanctioned
₹0 spent (0%)