Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:36:19.743515
Works ongoing
75
Sanctioned (pure scheme)
₹72.47 L
Expenditure since inception
₹52.95 L
Balance cost (unspent)
₹19.52 L
Wage ₹12.98 L · Material ₹6.54 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Slowest spending this week — worth a look
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
10 works
₹23.32 L sanctioned
₹15.93 L spent (68%)
02
Rural Housing
59 works
₹13.86 L sanctioned
₹13.05 L spent (94%)
03
Construction of Check Dam/Stop Dam
1 works
₹13.40 L sanctioned
₹11.81 L spent (88%)
04
Construction of Tank
1 works
₹10.54 L sanctioned
₹5.86 L spent (56%)
05
Construction of Trench
1 works
₹9.18 L sanctioned
₹4.72 L spent (51%)
06
Well Recharge
1 works
₹99,998 sanctioned
₹51,936 spent (52%)
07
Cattle Shed
1 works
₹62,951 sanctioned
₹60,002 spent (95%)
08
Goat Shelter
1 works
₹54,879 sanctioned
₹46,278 spent (84%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)