Monitor — Ongoing Works

Rollup last refreshed: 2026-08-27 14:06:46.546602
to
Reset filters
Works ongoing
1,965
Sanctioned (pure scheme)
₹39.11 Cr
Expenditure since inception
₹18.82 Cr
Balance cost (unspent)
₹20.30 Cr
Wage ₹11.43 Cr · Material ₹8.87 Cr
Expenditure trend
−₹1.49 Cr
This Week
−₹1.47 Cr
Last Week
▼ 1.6% vs last week
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹90.28 L
Mandays trend
-94,475
This Week
-1,36,226
Last Week
▲ 30.6%
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-53,337

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
310 works
₹15.02 Cr sanctioned
₹6.12 Cr spent (41%)
02
Construction of Well
104 works
₹3.62 Cr sanctioned
₹2.19 Cr spent (60%)
03
Constr of Cement Concrete Roads
31 works
₹3.19 Cr sanctioned
₹1.77 Cr spent (56%)
04
Rural Housing
1,317 works
₹3.09 Cr sanctioned
₹1.69 Cr spent (55%)
05
Solid and Liquid Waste Management
27 works
₹2.85 Cr sanctioned
₹1.60 Cr spent (56%)
06
Construction of Road and Culvert
20 works
₹2.68 Cr sanctioned
₹2.05 Cr spent (76%)
07
Construction of Tank
15 works
₹1.99 Cr sanctioned
₹77.98 L spent (39%)
08
Land Development
21 works
₹1.34 Cr sanctioned
₹57.21 L spent (43%)
09
Construction of Percolation Tank
26 works
₹1.08 Cr sanctioned
₹40.15 L spent (37%)
10
Construction of Bund
12 works
₹87.22 L sanctioned
₹32.65 L spent (37%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 1,317 3.09 1.69 1.40
55%
2 Plantation 310 15.02 6.12 8.90
41%
3 Construction of Well 104 3.62 2.19 1.43
61%
4 Constr of Cement Concrete Roads 31 3.19 1.77 1.42
56%
5 Farm Pond 28 0.43 0.13 0.30
30%
6 Solid and Liquid Waste Management 27 2.85 1.60 1.25
56%
7 Construction of Percolation Tank 26 1.08 0.40 0.67
37%
8 Land Development 21 1.34 0.57 0.77
43%
9 Construction of Road and Culvert 20 2.68 2.05 0.64
76%
10 Construction of Check Dam/Stop Dam 16 0.64 0.23 0.41
36%
11 Construction of Tank 15 1.99 0.78 1.21
39%
12 Construction of Bund 12 0.87 0.33 0.55
37%
13 Well Recharge 7 0.43 0.17 0.25
41%
14 Construction of NADEP/Vermi Compost Pit 6 0.02 0.01 0.01
61%
15 Constr of Aganwadi 6 0.11 0.06 0.05
54%
16 Repair & maint of Pond/ Tank 5 0.46 0.25 0.22
53%
17 Grass Land Development 4 0.38 0.24 0.14
63%
18 Constr of Compound wall 2 0.26 0.10 0.16
37%
19 Construction of Canal 1 0.06 0.01 0.05
12%
20 Cattle Shed 1 0.38 0.00 0.38
0%
21 Constr of Food Grain storage 1 0.00 0.00 0.00
56%
22 Construction of building/workshed for SHG 1 0.09 0.08 0.01
89%
23 Construction of Crematorium 1 0.02 0.02 0.00
87%
24 Construction of Recharge Pits 1 0.00 0.00 0.00
5%
25 Construction of Trench 1 0.05 0.00 0.04
4%
26 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.04 0.01 0.03
33%
Total 1,965 39.11 18.82 20.30
All 26 rows (zero-value rows hidden) ⇩ Export to Excel