Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
Reset filters
Works ongoing
1,976
Sanctioned (pure scheme)
₹39.14 Cr
Expenditure since inception
₹18.67 Cr
Balance cost (unspent)
₹20.47 Cr
Wage ₹11.58 Cr · Material ₹8.88 Cr
Expenditure trend
₹36.31 L
This Week
₹56.93 Cr
Last Week
▼ 99.4% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Slowest spending this week — worth a look
  • JABALPUR — SHAHPURA−₹3.49 L
Mandays trend
20,131
This Week
2,63,410
Last Week
▼ 92.4%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Lowest mandays this week — worth a look
  • DHAR — DHARAMPURI-1,460

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
310 works
₹15.02 Cr sanctioned
₹6.04 Cr spent (40%)
02
Construction of Well
104 works
₹3.62 Cr sanctioned
₹2.15 Cr spent (59%)
03
Constr of Cement Concrete Roads
31 works
₹3.19 Cr sanctioned
₹1.78 Cr spent (56%)
04
Rural Housing
1,328 works
₹3.12 Cr sanctioned
₹1.65 Cr spent (53%)
05
Solid and Liquid Waste Management
27 works
₹2.85 Cr sanctioned
₹1.61 Cr spent (56%)
06
Construction of Road and Culvert
20 works
₹2.68 Cr sanctioned
₹2.04 Cr spent (76%)
07
Construction of Tank
15 works
₹1.99 Cr sanctioned
₹93.97 L spent (47%)
08
Land Development
21 works
₹1.34 Cr sanctioned
₹55.76 L spent (42%)
09
Construction of Percolation Tank
26 works
₹1.08 Cr sanctioned
₹39.61 L spent (37%)
10
Construction of Bund
12 works
₹87.22 L sanctioned
₹28.48 L spent (33%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 1,328 3.12 1.65 1.46
53%
2 Plantation 310 15.02 6.04 8.98
40%
3 Construction of Well 104 3.62 2.15 1.47
59%
4 Constr of Cement Concrete Roads 31 3.19 1.78 1.42
56%
5 Farm Pond 28 0.43 0.13 0.30
30%
6 Solid and Liquid Waste Management 27 2.85 1.61 1.25
56%
7 Construction of Percolation Tank 26 1.08 0.40 0.68
37%
8 Land Development 21 1.34 0.56 0.78
42%
9 Construction of Road and Culvert 20 2.68 2.04 0.64
76%
10 Construction of Check Dam/Stop Dam 16 0.64 0.23 0.41
36%
11 Construction of Tank 15 1.99 0.94 1.05
47%
12 Construction of Bund 12 0.87 0.28 0.59
33%
13 Well Recharge 7 0.43 0.17 0.26
41%
14 Construction of NADEP/Vermi Compost Pit 6 0.02 0.01 0.01
61%
15 Constr of Aganwadi 6 0.11 0.06 0.05
54%
16 Repair & maint of Pond/ Tank 5 0.46 0.25 0.22
54%
17 Grass Land Development 4 0.38 0.24 0.14
63%
18 Constr of Compound wall 2 0.26 0.10 0.16
37%
19 Construction of Canal 1 0.06 0.01 0.05
12%
20 Cattle Shed 1 0.38 0.00 0.38
0%
21 Constr of Food Grain storage 1 0.00 0.00 0.00
56%
22 Construction of building/workshed for SHG 1 0.09 0.01 0.08
9%
23 Construction of Crematorium 1 0.02 0.02 0.00
87%
24 Construction of Recharge Pits 1 0.00 0.00 0.00
5%
25 Construction of Trench 1 0.05 0.00 0.04
4%
26 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.04 0.01 0.03
33%
Total 1,976 39.14 18.67 20.47
All 26 rows (zero-value rows hidden) ⇩ Export to Excel