Monitor — Ongoing Works
Rollup last refreshed: 2026-10-18 06:53:07.800224
Works ongoing
7
Sanctioned (pure scheme)
₹9.22 L
Expenditure since inception
₹22,800
Balance cost (unspent)
₹8.99 L
Wage ₹3.98 L · Material ₹5.01 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹48.31 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
3 works
₹8.00 L sanctioned
₹0 spent (0%)
02
Roof Water Harvesting on gov/panchayat bldg
4 works
₹1.22 L sanctioned
₹22,800 spent (19%)
03
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
04
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
05
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)
06
Plantation
0 works
₹0 sanctioned
₹0 spent (0%)