Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
27
Sanctioned (pure scheme)
₹46.35 L
Expenditure since inception
₹21.57 L
Balance cost (unspent)
₹24.78 L
Wage ₹15.49 L · Material ₹9.29 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹19.63 L sanctioned
₹9.69 L spent (49%)
02
Construction of Well
3 works
₹11.82 L sanctioned
₹3.67 L spent (31%)
03
Plantation
2 works
₹5.39 L sanctioned
₹1.31 L spent (24%)
04
Rural Housing
16 works
₹3.71 L sanctioned
₹2.75 L spent (74%)
05
Constr of Compound wall
1 works
₹3.09 L sanctioned
₹2.32 L spent (75%)
06
Construction of Percolation Tank
1 works
₹1.49 L sanctioned
₹80,523 spent (54%)
07
Constr of Cement Concrete Roads
2 works
₹1.22 L sanctioned
₹1.02 L spent (83%)
08
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Trench
0 works
₹0 sanctioned
₹0 spent (0%)