Monitor — Ongoing Works
Rollup last refreshed: 2026-08-26 17:54:53.293656
Works ongoing
57
Sanctioned (pure scheme)
₹37.84 L
Expenditure since inception
₹28.57 L
Balance cost (unspent)
₹9.28 L
Wage ₹4.97 L · Material ₹4.30 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
3 works
₹11.57 L sanctioned
₹8.51 L spent (74%)
02
Rural Housing
49 works
₹11.51 L sanctioned
₹8.93 L spent (78%)
03
Farm Pond
3 works
₹7.09 L sanctioned
₹4.70 L spent (66%)
04
Land Development
1 works
₹4.57 L sanctioned
₹4.48 L spent (98%)
05
Plantation
1 works
₹3.10 L sanctioned
₹1.95 L spent (63%)
06
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)