Monitor — Ongoing Works
Rollup last refreshed: 2026-09-01 08:57:48.415109
Works ongoing
19
Sanctioned (pure scheme)
₹27.02 L
Expenditure since inception
₹14.38 L
Balance cost (unspent)
₹12.64 L
Wage ₹6.91 L · Material ₹5.73 L
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Farm Pond
3 works
₹9.86 L sanctioned
₹7.06 L spent (72%)
02
Construction of Well
3 works
₹8.20 L sanctioned
₹5.33 L spent (65%)
03
Plantation
3 works
₹6.22 L sanctioned
₹80,809 spent (13%)
04
Rural Housing
6 works
₹1.62 L sanctioned
₹89,559 spent (55%)
05
Constr of Cement Concrete Roads
1 works
₹67,560 sanctioned
₹24,273 spent (36%)
06
Construction of Trench
3 works
₹43,402 sanctioned
₹3,882 spent (9%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Other Community Building/Assets
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)