Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:36:19.743515
Works ongoing
16
Sanctioned (pure scheme)
₹37.03 L
Expenditure since inception
₹24.38 L
Balance cost (unspent)
₹12.64 L
Wage ₹6.04 L · Material ₹6.60 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Slowest spending this week — worth a look
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹19.61 L sanctioned
₹19.57 L spent (100%)
02
Construction of Well
2 works
₹5.83 L sanctioned
₹1.75 L spent (30%)
03
Plantation
3 works
₹5.38 L sanctioned
₹9,985 spent (2%)
04
Solid and Liquid Waste Management
1 works
₹4.11 L sanctioned
₹1.27 L spent (31%)
05
Rural Housing
9 works
₹2.10 L sanctioned
₹1.70 L spent (81%)
06
Construction of building/workshed for SHG
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)